Case Study:
Emergency Call Out
Project
A local leisure facility had a gas boiler fail overnight, resulting in a loss of heating for the leisure facility and the hotel residents were occupying.
​
B-engineering was asked to provide an emergency attendance to ensure the gas services were safe, the failed boiler would not cause any further risk, and to assist the facility in implementing a temporary solution to provide heating.


Delivery
Utilising the in-house gas specialists, the B-engineering group ensured that the gas devices service remained safe and safely isolated the failed boiler.
​
New connections to the existing LTHW system were welded in position to accommodate a temporary boiler, and a new gas main supply was provided to the boiler.
​
​Working from 8 a.m through midnight to ensure the facility had suitable heating, all works were delivered by in-house engineers. Working from 8 am until past midnight to ensure the facility had suitable heating, all work was delivered by in-house engineers.
Benefits
Due to the fast response and the multi-skilled team available, we were able to assist the facility in gaining a heating solution in a very short turnaround time.
​
This fast response ensured the facility could remain open and avoid closing —preventing huge losses.