Olam Food Ingredients
Case Study: Solar PV
The project for Olam International involved fitting a 170kWh Solar PV system on two buildings to decarbonize their operations. One building was a smaller production facility with most of the site's electrical load, while the other was a larger warehouse with minimal electrical usage.
Project
Delivery
The project for Olam International involved fitting a 170kWh Solar PV system on two buildings to decarbonize their operations. One building was a smaller production facility with most of the site's electrical load, while the other was a larger warehouse with minimal electrical usage.
Benefits
The solar array is estimated to generate around 159,376kWh annually, providing significant environmental benefits by reducing carbon emissions. Through this project, Olam International has taken a significant step towards sustainability by utilizing renewable energy sources and optimizing their energy consumption.
Projection PA
ROI 3.3 Year
33,78.8 Kg COâ‚‚ Reduction
£49,000 Projected Saving
165,894 KWH Production